|
back | home > society > policy > nepa
The National Environmental Policy Act of
1969
Major Relevant Cases (Annotated)*
General
Hanly v. Kleindienst 471 F.2d
823 (2nd Circ. 1972)
This case weighs the interpretation of the word "significantly" in
the critical NEPA phrase "major Federal actions significantly
affecting the quality of the human environment" (42
U.S.C. § 4332(C)), as it is applied to the proposed
construction of a Manhattan federal building. In determining
whether the effects of the project were significant (and
therefore whether the responsible agency would be required
to prepare an environmental impact statement), two criteria
were used: the extent of adverse environmental effects beyond
those created by existing uses of the area and the extent
of absolute adverse effects, including the cumulative effect
of existing conditions. The ruling also established that
the appropriate criterion for threshold determinations was
the "arbitrary, capricious . . . " standard found
in the Administrative Procedure Act (§ 10(e)).
Strycker's Bay Neighborhood Council,
Inc. v. Karlen 444 U.S. 223 (1980)
The Supreme Court ruled that NEPA is a strictly procedural
document. The Department of Housing and Urban Development
was not required to select an environmentally preferable
alternate site for a Manhattan housing project. The Court
found it sufficient that the agency had appropriately considered
a reasonable range of alternatives according to NEPA procedure
and had ruled out the environmentally preferable site because
it would cause delays in construction.
Fire Related
National Helium Corp. v. Morton,
455 F.2d 650 (10th Cir. 1971)
A federal decision not to act was defined as a major federal
action when the Department of the Interior decided not to
stockpile helium. The court ruled that the "rapid depletion
of the helium resources of the country" was an environmental
consequence of the "no action" decision. The determination
of significance was left up to the Secretary of the Interior,
but the clear result was that the decision not to act is
subject to NEPA. This ruling has obvious implications for
fire management; an agency making an overt decision not to
address a hazardous fuels situation must go through the NEPA
process, just as it would if it were proposing a concrete
action.
* Adapted in part from Weinberg (2001)
and Coggins et al. (2001).
summary | flowchart |
cases | document | CEQ
NEPA Regulations | references
|